Our Projects

PSP Project : Gujjili

Pumped Storage PSP 2
krishnapatnam-solar-banner
2,400 MW
Capacity
634 m / 656 m
Design Head
2026
Construction
2030
Commission

Project Overview

2,400 MW off-river close loop cycle pumped storage project in Andhra Pradesh, designed with significant elevation head and long-distance transmission line infrastructure. Construction will begin in 2026 with commissioning expected by 2030.

Upper Reservoir & Geological Aspects

67.0 m high, 475 m long GFRD with 12.27 MCM live storage.

Lower Reservoir & Geological Aspects

42.0 m high, 885 m long GFRD with 12.27 MCM live storage.

Key Features

  • Off-river, close loop cycle
  • 634.0 m (generation) / 656.0 m (pumping) design head
  • 30.0 km 400 kV DC transmission line
  • 10 km pipe line from nearest source for initial filling
  • Feasibility completed, DPR in progress